Productivity in the construction industry
Constructing Excellence and BRE Academy to discuss the burning issues of productivity and efficiency and how they can be improved.
In the manufacturing industry, productivity increasing means better margins and improved efficiency within projects, and there are lessons that can be learned from this to aid organisations and supply chains within the construction industry.
BRE Buzz put some questions to Don Ward, Chief Executive of Constructing Excellence, and Simon Cross, Director of BRE SiteSmart, who sits on the Construction Leadership Council.
BRE Buzz:
First of all how would you measure productivity in construction?
Don Ward (DW):
Productivity is a measure of output/input or efficiency, rather than a measure of quality, effectiveness or value and in that sense we risk focusing on the wrong issues. Nevertheless, if we need a measure, then it would be earned value/person-hours, expressed as £K/person-year to enable sector and international comparisons.
However, ultimately we do need to focus on measuring outcomes, in terms of economic impact on the rest of the economy. We also need a more holistic look at analysing productivity that takes into account an increased used of offsite manufacturing.
Simon Cross (SC):
Construction productivity can be measured at macro and micro scale, the former at asset value (output achieved) for the sector and the latter as how much to a specific project asset. At macro scale productivity is typically £ generated per man hour, and at micro scale it could be £ to construct versus m2 covered for a building.
The micro scale units will depend on the type of project, building or infrastructure, and are a measure of how much cost to build, rather than value created.
BRE Buzz:
What is stopping companies from improving productivity of their workforce?
DW:
A thoroughly flawed process – from procurement to delivery – that lacks integration, collaboration, a holistic project-level and whole life view. All this impedes the uptake of digital, automated and offsite approaches.
SC:
Constructors typically lack capital investment, they are stuck in a cycle of low margins leading to low capital. Often contractors work at less than 1% margin. Raising capital is therefore very hard. Low capital leads to low investment in new technologies and skills. Traditional projects are built on packaged prices with contractors and subcontractors, and the nature of these business models and contract types is not always collaborative.
BRE Buzz:
Can and should companies improve the way they engage their supply chain?
DW:
Yes this is essential throughout the supply chain. It starts with the clients and their initial appointments of consultants and Tier 1 contractors, with the latter adopting the same principles in procuring subcontractors and materials. Hastily arranged one-off subcontracting arrangements bought on lowest tender price are not supply chains.
Surely the sector is now close to a tipping point to make this breakthrough via for offsite approaches enabled by digital adoption, fuelled by client appetite.
SC:
Yes, collaboration with joint risk mitigation is key to delivering a project well. Early engagement with the right form of contract creates a better plan, and a better opportunity of success.
BRE Buzz:
How can BIM best aid the productivity on site?
DW:
Eliminate or at least reduce the duplication of data and information by providing one source of the truth for all project participants. The use of BIM both requires and enables better integration and collaboration of the project team, so the benefits extend far beyond this into facilitating lean approaches and eliminating waste in all its forms.
SC:
BIM can be used across the supply chain as a flow of good information for decision making. Moving through the BIM levels will enable increased design and construction data sharing, aiding better decision making and collaboration between parties.
BRE Buzz:
What types of data collected on site provide meaningful information for improving productivity on existing and future projects?
DW:
Safety, accidents, incidents; productive versus waiting time; site waste data. Much of this is collected by BRE’s excellent SiteSmart toolkit.
SC:
A full range of information can be collected: build/capital cost; speed/programme reduction; productivity; quality/defects; health& safety; in-use energy performance; material usage and waste.
BRE Buzz:
What key lessons can construction learn from manufacturing?
DW:
Establish a reliable predictable process and then continuously improve it by engaging the workforce and supply chain. Target automation and digital wherever possible, and move towards offsite production wherever possible because it delivers better safety, better quality, better reliability/predictability, and speed. And with critical mass, cost savings will also follow.
SC:
Advanced manufacturing and driven productivity in the manufacturing substantially over the past 20 years. Adding value has been achieved through new technologies and automation, better standards and design, new business models, including sales, operations and technical. Improving skills for project management, lean design and delivery.
This article was originally published here by BRE Buzz on 30 May 2017. It was written by Jo Goodwin.
--BRE Buzz
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.